What is the amount of time that a task can be delayed without affecting subsequent tasks?
Show
As per PMBOK the Float is defined as: The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. It can be calculated in two ways: Float = Late Start - Early Start OR Late Finish - Early Finish Critical Activities (activities on the Critical Path) usually have a Float of Zero by Ahmed Khater , ID& Fit- Out Construction Manager , Harmony Atelier Interior Design& Decoration Float or slack is the amount of time between early start and late start for an activity e.g. if you can now start an activity (which take one week to complete ) and its OK to complete it within3 weeks without delaying the completion of the project so the float here =2 weeks buffer time to complete the task or activity without causing delay to its interdependent tasks. Thanks.
by Ajaya Mohanty Ajaya , District Project Officer , Odisha State Disaster Management Authority In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float") project completion date ("total float"). by Fawzan Malas , Senior IT Consultant , Jumia Algeria Float or slack time is the amount of work periods an activity can be delayed without causing an overall delay to the project. There are two types of float: total float and free float. Total float is the amount of time you can delay the earliest start of a task without delaying the ending of the project. Free float is the amount of time you can delay the start of a task without delaying the earliest start of a successor task. by ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company This is the time duration to which the activity can be delayed without affecting the project duration by Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality I think that the subject needs some details ;- Free slack or free float is different than Total Float Free Float is the time an activity can be delayed without delaying its subsequent activities Total Float is the time an activity can be delayed without delaying the project completion date. There is no float time for activities on the critical path, that's why they are identified as being critical. by د Waleed , Management - Leadership-Business Administration-HR&Training-Customer Service/Retention -Call Center , Multi Companies Categories: Auditing -Trade
-Customer service -HR-IT&Internet -Training&Consultation I would agree with provided answers... Helpful information ... Thank You ! Float, is the time between the planned completion date of an activity in the schedule, and the date where it will become a critical path activity. Essentially, the extra time allowed in the schedule for an activity, before it will start to affect the overall completion date. by Ansu Batabyal , DESIGN ENGINEER , TATA CONSULTING ENGINEERS LTD. Schedule the project in bottom up approach with realistic time. Make more parallel activity with additional man power. Crash the schedule. Popular SearchesWhat term is used for the amount of time an activity can be delayed?Total Float (TF)
The amount of time that an activity can be delayed from its early start without delaying the project finish date.
What is the duration by which an activity can be delayed without delaying?The Interfering float is the time available to delay an activity without delaying the project\'s estimated completion time, but delaying an activity into interfering float will delay the start of one or more following non-critical activities.
Is the maximum length of time that an activity can be delayed without delaying the entire project?Slack is the amount of time an activity can be delayed without delaying the entire project.
Is the amount of time a schedule activity can be delayed without delaying the early start of any successor?Free Float, per definition, is the amount of time that the activity can be delayed before any successors will be delayed. Early Start/Finish times are used to calculate the Free Float values.
|